Proposed Construction and Completion of Kapit Wharf Waterfront, At Kapit, Phase II, Sarawak

Project Summary:

One of the projects that the firm handled and developed was the building of Kapit Wharf Waterfront with a contract value of RM 3,599,444.43. This project has become the town’s latest attraction to the local community and tourists who come to visit. In general, the contract comprises the supply of labour, plants, equipment, and materials for the construction of the civil works included in the contract. The scope of works includes preliminary works, piling works, building works, architecture and infrastructure works. The project started on 13/02/2019 and was completed on 18/10/2020, with an EOT period of 280 days due to MCO. Kapit District Council was the client for this project and Kalaka Jaya Sdn Bhd was appointed as the main contractor.